Project
Project Budget
Encumbrance
Spent to Date
% Complete
Bluesten Park $36,000,000.00 $1,693,901.92 $805,721.02 30% – Design phase
Golden Isles Tennis Center & Park $8,800,000.00 $10,921.40 $10,921.14 0%-Design Phase(Architect Contract award 9/21/16)
Ingalls Park $2,000,000 $6,500 $ 6,500 15% – Design Phase
Sunset Park $553,202 $13,482 $11,482 30% – Design Phase
Historic Village $ 617,579 $0 $0 0% – Architect Award Oct/Nov. 2016
Sunrise Park $3,200,000 $0 $0 0% – Project Commencing 2017
┬áChaves Lake Park $3,700,00 $0 $0 0% – Project Commencing 2017